A contract delivered within the specified time-frame and meeting our customers expectations.
This operation concerned lifting and erecting 10 boiler modules each weighing approximatively 261T, scheduled as a ten days operation, from the end of January 2009 until the beginning of February 2009. The time frame of the module per day was perfectly respected to the clients complete satisfaction.
The complexity of the operation lies in sheduling within transportation of the modules provided by SPMT directly on site and further by the system utilising two pulleys with a unit capacity of 145T, especially developed and manufactured for that shipyard.
Equipment used : DEMAG CC2800 with the following specification : 60 m of right arrow, 300 tonnes counter weight balance, Superlift with crane-foot / DEMAG AC800 with the following specification : 140 tonnes of counter balance weight at base.
|